Skip to content
  • The Consortia Group
    • Who we are
    • Meet the team
    • Sustainability
    • Social value
    • Accreditations & Certifications
  • News
  • Careers
  • Contact
  • The Consortia Group
    • Who we are
    • Meet the team
    • Sustainability
    • Social value
    • Accreditations & Certifications
  • News
  • Careers
  • Contact
  • Transport
  • Maintenance
  • Construction
  • Our work
  • Transport
  • Maintenance
  • Construction
  • Our work
  • Transport
  • Maintenance
  • Construction
  • Our work
  • The Consortia Group
    • Who we are
    • Meet the team
    • Sustainability
    • Accreditations & Certifications
    • Social value
  • News
  • Careers
  • Contact
  • Transport
  • Maintenance
  • Construction
  • Our work
  • The Consortia Group
    • Who we are
    • Meet the team
    • Sustainability
    • Accreditations & Certifications
    • Social value
  • News
  • Careers
  • Contact

Home » Greenbank Surgery Refurbishment

Greenbank Surgery Refurbishment

Client

Greenbank Drive Surgery

Location

Liverpool

Project Value

£135,000

Project duration

12 Weeks

Project overview

The Consortia Group was appointed to deliver the refurbishment of Greenbank Surgery, initially focused on the ground floor reception and treatment room. As the project progressed, the scope expanded to include the redecoration of the first floor and upper floor offices, together with additional improvements that enhanced the functionality, accessibility and overall environment of the practice.

A key priority throughout the project was ensuring the surgery remained fully operational, allowing patients and staff to continue accessing essential healthcare services with minimal disruption.

Approach

Maintaining uninterrupted access to the surgery while undertaking extensive refurbishment works required careful planning and close collaboration with the client.

During the project, an unforeseen issue was identified when the existing upper floor ceilings were found to be unsafe due to the delamination of the original plaster. Recognising the potential risk, we immediately implemented temporary protection measures to safeguard occupants and prevent further deterioration.

Within 12 hours of identifying the issue, we had engaged a structural engineer to carry out a detailed survey, enabling informed decisions to be made quickly. Working alongside the client, we developed a practical solution that allowed the ceiling replacement works to be completed with minimal impact on the day-to-day operation of the surgery.

To further reduce disruption, several elements of the programme were delivered during night shifts, particularly where works could have affected patient access or clinical services.

Collaboration and Communication

Close communication with the client was fundamental to the successful delivery of the project. As the scope evolved and unexpected structural issues emerged, we maintained regular dialogue to ensure decisions could be made quickly and programme impacts were minimised.

Our proactive approach enabled additional works to be incorporated without compromising the continued operation of the surgery. By coordinating works around clinical activities and undertaking high-impact tasks outside normal operating hours, we ensured patients and staff experienced as little disruption as possible.

Value Engineering

Throughout the project, we worked collaboratively with the client to identify solutions that provided the best long-term value without compromising quality or safety.

Following the discovery of the defective ceilings, we reviewed the proposed replacement works to reduce unnecessary costs while maintaining compliance and performance. In addition, The Consortia Group reduced its usual profit margin on the ceiling replacement works, helping the client manage the unforeseen additional expenditure resulting from the latent defect.

Scope of works

  • Ground floor reception and treatment room refurbishment.
  • Office and meeting room upgrades across upper floors.
  • Reception alterations, including new DDA-compliant desk.
  • Automated entrance doors and improved accessibility.
  • Replacement fire doors and unsafe ceilings.
  • New flooring, carpets and internal decoration.
  • LED lighting and electrical upgrades.
  • Data, power and mechanical alterations.
  • Floor preparation, fire stopping and making good works.

Outcome

Programme and Quality Management

Maintaining programme certainty while accommodating an expanding scope of works required careful planning and flexible resource management.

Works were sequenced to allow the surgery to remain operational throughout the project, with night working utilised where interfaces with patients or clinical staff could not be avoided.

Quality was maintained through regular inspections, close supervision and ongoing coordination with the client and specialist contractors. The rapid appointment of a structural engineer following the discovery of the ceiling defects demonstrated our proactive approach to risk management and our commitment to delivering safe, high-quality outcomes.

Outcome

The completed refurbishment has transformed Greenbank Surgery into a more modern, accessible and welcoming healthcare environment for patients, visitors and staff.

Despite the challenges presented by the live healthcare setting and the unforeseen structural ceiling issues, the project was delivered safely and with minimal disruption to the surgery’s daily operations. Through collaborative working, responsive problem-solving and a commitment to quality, The Consortia Group successfully delivered a refurbishment that not only met the client’s original objectives but also incorporated additional improvements that enhanced the longevity, safety and functionality of the building.

Summary

The Consortia Group was appointed to deliver the refurbishment of Greenbank Surgery, initially focused on the ground floor reception and treatment room. As the project progressed, the scope expanded to include the redecoration of the first floor and upper floor offices, together with additional improvements that enhanced the functionality, accessibility and overall environment of the practice.

A key priority throughout the project was ensuring the surgery remained fully operational, allowing patients and staff to continue accessing essential healthcare services with minimal disruption.

Scope of works

  • Ground floor reception and treatment room refurbishment.
  • Office and meeting room upgrades across upper floors.
  • Reception alterations, including new DDA-compliant desk.
  • Automated entrance doors and improved accessibility.
  • Replacement fire doors and unsafe ceilings.
  • New flooring, carpets and internal decoration.
  • LED lighting and electrical upgrades.
  • Data, power and mechanical alterations.
  • Floor preparation, fire stopping and making good works.

Approach

Maintaining uninterrupted access to the surgery while undertaking extensive refurbishment works required careful planning and close collaboration with the client.

During the project, an unforeseen issue was identified when the existing upper floor ceilings were found to be unsafe due to the delamination of the original plaster. Recognising the potential risk, we immediately implemented temporary protection measures to safeguard occupants and prevent further deterioration.

Within 12 hours of identifying the issue, we had engaged a structural engineer to carry out a detailed survey, enabling informed decisions to be made quickly. Working alongside the client, we developed a practical solution that allowed the ceiling replacement works to be completed with minimal impact on the day-to-day operation of the surgery.

To further reduce disruption, several elements of the programme were delivered during night shifts, particularly where works could have affected patient access or clinical services.

Collaboration and Communication

Close communication with the client was fundamental to the successful delivery of the project. As the scope evolved and unexpected structural issues emerged, we maintained regular dialogue to ensure decisions could be made quickly and programme impacts were minimised.

Our proactive approach enabled additional works to be incorporated without compromising the continued operation of the surgery. By coordinating works around clinical activities and undertaking high-impact tasks outside normal operating hours, we ensured patients and staff experienced as little disruption as possible.

Value Engineering

Throughout the project, we worked collaboratively with the client to identify solutions that provided the best long-term value without compromising quality or safety.

Following the discovery of the defective ceilings, we reviewed the proposed replacement works to reduce unnecessary costs while maintaining compliance and performance. In addition, The Consortia Group reduced its usual profit margin on the ceiling replacement works, helping the client manage the unforeseen additional expenditure resulting from the latent defect.

Sectors

Loading...

Healthcare

Services

Loading...

Construction

Installation / Fit-out

Team

Loading...

Outcome

Programme and Quality Management

Maintaining programme certainty while accommodating an expanding scope of works required careful planning and flexible resource management.

Works were sequenced to allow the surgery to remain operational throughout the project, with night working utilised where interfaces with patients or clinical staff could not be avoided.

Quality was maintained through regular inspections, close supervision and ongoing coordination with the client and specialist contractors. The rapid appointment of a structural engineer following the discovery of the ceiling defects demonstrated our proactive approach to risk management and our commitment to delivering safe, high-quality outcomes.

Outcome

The completed refurbishment has transformed Greenbank Surgery into a more modern, accessible and welcoming healthcare environment for patients, visitors and staff.

Despite the challenges presented by the live healthcare setting and the unforeseen structural ceiling issues, the project was delivered safely and with minimal disruption to the surgery’s daily operations. Through collaborative working, responsive problem-solving and a commitment to quality, The Consortia Group successfully delivered a refurbishment that not only met the client’s original objectives but also incorporated additional improvements that enhanced the longevity, safety and functionality of the building.

More case studies

View all

Newcastle Central Station

Liverpool Rail House Remodelling Works

Newcastle Station – Ticket Sales Unit

Berwick-Upon-Tweed Station – Travel Centre

York Station – Reconfigure Former Ballroom

York Station – Academy Building

Clatterbridge Cancer Centre MRI Scanner Removal

Honley High School – Glazed Walkway

Middlesborough Station – Staff Accommodation Works

Penny Lane Surgery Refurbishment

Paddington Station – Assisted Travel Lounge

SWR Waiting Shelters

Sheffield Station

London Liverpool Street

Plymouth Station Refurbishment

University of Liverpool Chemistry Department

Worksop Station Enhancements

Birmingham Coach Station Concourse

National Express Office Refurbishment

National Express Dilapidations Works

Glossop Station

Perth Railway Depot

Eastfield Railway Depot

Bridgewater Forecourt

Sign up to our newsletter

Sign up
  • Transport
  • Services
  • Transport works
  • Dedicated team
  • Our clients
  • Transport
  • Services
  • Transport works
  • Dedicated team
  • Our clients
  • transport@theconsortiagroup.com
  • Maintenance
  • Services
  • Sectors
  • Maintenance works
  • Dedicated team
  • Our clients
  • Maintenance
  • Services
  • Sectors
  • Maintenance works
  • Dedicated team
  • Our clients
  • maintenance@theconsortiagroup.com
  • Construction
  • Services
  • Sectors
  • Construction works
  • Dedicated team
  • Our clients
  • Construction
  • Services
  • Sectors
  • Construction works
  • Dedicated team
  • Our clients
  • construction@theconsortiagroup.com

6 Columbus Quay,
Liverpool, L3 4DB
0151 294 3114

Linkedin
  • info@theconsortiagroup.com

Accreditations

The Consortia Group

  • Who we are
  • Meet the team
  • Social Responsibility
  • Sustainability
  • Accreditations & Certifications
  • News
  • Contact
  • Privacy Policy
  • Cookie Policy (UK)
  • Who we are
  • Meet the team
  • Social Responsibility
  • Sustainability
  • Accreditations & Certifications
  • News
  • Contact
  • Privacy Policy
  • Cookie Policy (UK)

© Consortia Integrated Services 2021

  • Privacy policy
  • Customer commitment statement

Website by 39steps

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behavior or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}